Case Studies > Hybris Limited > Copthall Avenue

Project Overview

CAT B refurbishment of 3,500f2 5th floor office space, works included the formation of open plan office accommodation for 30 workstations, boardroom, two meeting rooms, comms room, kitchen and break out area, and reception.

Works included

Challenges

Timeframe: The most challenging aspect of this project was the short time frame, which was dictated by the surrender date on the clients existing lease. In addition the rest of the building was occupied which severely restricted the time available for loading out, isolation of services and noisy work.

Safe methods of working needed to be developed within the stairwells which where the only means of access to the floors by the occupants and residents of the top floor apartments.